Your present position: Technology >>Anti-static aerial activity is on the floor construction plan


Composition:

    The anti-static floor of the main three parts, the bottom is a derivative of copper electricity network (non-essential items), in the middle of the main supporting frames for the upper + motherboard is laying on the surface material (non-essential). Supporting frames from the main frame, beams, as well as accessories such as the composition of the Rose.

   

Base can be a high degree of adjustment in order to maintain a high degree of consensus, and have been galvanized to deal with, a good anti-corrosion moisture, the floor beams to share the load-bearing activities to improve the overall stability of the tab panel fixed location, noise and static electricity discharge.

Time to install:
Skilled workers, in a normal room, about 50 square meters / per person per day. Above estimates do not include materials preparation, handling and processing time. Rules laid on the ground floor of the savings of 20-30% for their installation. At the same time, good preparation and well-planned installation can also save a lot of time to install.

Construction tools recommended:

Recommended installation tools

Applications

An electric drill

Fixed around the corner and

Cutting Saw

Cutting board

The level of infrared device, the level of foot

Calibration standard and maintain the board planing

Rose knives, hand in hand, hammer, nail gun and Latin America, hand-clamp

Regulation, motherboard, frame, Rose, received a fixed margin

Tape measure, Gang Chi, Modou, pencil

Measurement, line

Sucker on the floor

Mobile, the replacement of the floor

Anti-static flooring system features:
※ anti-static floor activities can only be used indoors;
※ anti-static floor addition to the activities of the special needs of not laying on the surface decoration materials;
※ effective to prevent static electricity; effective flame retardant;
※ Naizang surface, non-slip, corrosion-resistant chemical products;
※ strong resistance on the surface, not blistering, no degumming, long life;
※ Shanghai Baoshan Iron and Steel materials used, pressure, impact resistance; Ma-to-date at the end of plastic spray to prevent rust bottom, to extend life;
※ simple to install and easy to check wiring, and easy to manage.

The beginning of construction:

→ positioning reference point: an appropriate reference point, you can save material loss, spare parts and construction time, it is the best choice at right angles to the wall when the two sides of the same baseline.
→ slope if the door or doors left room for maneuver, should be near the entrance to get better reference point.
→ design or partition map on the plane, has been marked by the reference point when drawing prevail.

Note:
Baseline: parallel to the base level by drawing a straight line with the base-level baseline for the maximum distance between the 600mm.
Datum: to identify the owners of the entire board to be installed on a wall.
Vertical lines: perpendicular to the baseline of a straight line, vertical line with the maximum distance of the wall adjacent to 600mm

Pre-construction preparations:
→ first design drawings in accordance with the requirements prior to the laying on the floor of the grass-roots activities to do a good job (most of the ground or cement mill system is on the ground, etc.), the surface of the grass-roots level should be smooth, bright and clean, not dust, moisture content of not more than 8% of the installation Should be cleaned and, if necessary, brushing the surface of insulation in their fat or paint. So flat rectangular room, its walls must be adjacent to each other vertical.
→ activities to install the floor surface, the interior must be completed over the floor and the surface of the bearing capacity of equipment is scheduled to enter the room after the purchase would be required, construction can not cross; exceptional circumstances such as the need to cross the construction, I should be in strict accordance with Secretary "cross the floor construction to maintain that" operations.
→ activities set up on the floor surface, check to check the ground surface elevation, should be consistent with the design requirements. Interior walls will be around to draw the horizon elevation control.
→ to set up a large area before construction of large off-like, and do a model, by the quality inspection departments before they can be identified by the organization a model for inter-construction requirements.

The installation of anti-static floor activities:
→ first clean up the ground. Observation of the layout of the room, installed the level of infrared scanners, in the surrounding wall Banyao a good level, and then find the lowest point of the room and the highest point on the ground to calculate the average surface plate (equal to the average of the Party Required to install high), the calculation of a high degree of support and good conditioning.
→ election as a starting point for a corner in the wall to find a good level, according to the needs of a high level of the wall, the wall from the Department 595mm tying two parallel walls of the La-line, the Prince and the extension of the fault line is not easy, the two must be vertical Distribution.
→ parallel to the line and Latin America well, screw four good pay support. Determine the height of the first paved a board must be tightened with the support beams of fixed screws, and then use the level of tune-foot flat-panel, the last lock nut on the stent.
→ the first level of a tune, according to La-line vertical direction lay a good two rows on the floor. Note: The board and the board must be between the black plastic side alignment, straight.
→ two vertical row Puwan floor, look for a direction (vertical can no longer lay) have to take a line parallel to the laying of a row until the last row. Note: The four-week stay must be booked through the end of a cutting finishing laying, laying on the way, the board may not face any action step, so as not to affect flatness.
→ Puwan final in a row, should be fixed around the corner of angle iron, and then cut around the floor. Note: the level of angle iron to be installed with a good level of the floor, angle iron on the back of the structures must be (or the Sanjiao Tie-side support to support).
→ fixed angle iron, to be precise cutting a small piece of floor area, and then cutting the laying on the floor, to install additional outlets, the cutting machine with the actual opening size.
→ closed while anti-static floor, wall or door frames, columns, depending on the actual size of an electric saw to cut boards, or install the appropriate side parts. Closed doors with stainless steel or aluminum angle (right angle type) glass gluing or screw fastening and Latin America. Pu Wan on the floor, have to check in a timely manner, the better to adjust any acts of injustice, the last corner while plastic glass filled the gap left by the cutting.
→ If the temperature difference between day and night at the construction site environment (such as high-altitude, cold or temperate regions), all of the land side, should be set aside about 3 mm gap in order to adapt to heat up Lengsuo.

Construction Notes:
※ elevated position on the floor of the support (to whichever setting) does not allow any other construction obstructions placed.
※ has finished construction of the floor surface without the use of pre-delivery are not free to stampede, if construction of cross-borrowing needs of the floor when the stampede,
※ I have to be before the company agreed to be on-site management.
※ floor surface without the protection of the mosaic, are not allowed to use any construction work on the floor. ※ the surface of the floor should not be used for any heavy-duty scaffolding.
※ construction of the use of ladders, scaffolding at the bottom of the light must be tied with thick rubber. ※ Construction of the units is strictly prohibited the use of the surface of the floor in the paint, coatings, chemicals and materials.
※ Construction of the units is strictly prohibited to use a hammer or heavy objects hit the floor surface.
※ strictly prohibit the use of the surface of the floor tool and depicts a hard object.
※ If welding work must be on the floor plus a surface layer of protection, such as plywood, welding sparks come into contact with the floor is strictly prohibited.
※ strictly prohibit dumping below the surface of the floor.

Acceptance:
※ When the anti-static activities after the completion of the laying on the floor all, the whole project calls for detailed and thorough examination of problems with an improvement.
※ activity on the floor after running the installation must be no sound, no swing, a solid good.
※ surface clean, clear mission design, color, uniformity of the joints, surrounding straight, crack-free plate, off angle, and the lack of blistering edge and so on.
※ Department adjacent to a variety of surface materials and rimmed with size in line with the requirements of the design and construction norms provides tidy corner, smooth.

Per square meter calculated by the number of ingredients:
The main auxiliary parts list

The activities of anti-static floor

Parts name

Model specifications

Amount

GB

600mm × 600mm × 30mm

Stent

100~ 1000mm

3.3 pay

Beams

22 × 26 × 0.8mm

5.4 Support

Rose

6 × 32mm

10.8

GB

600mm × 600mm × 35mm

Stent

100~ 1000mm

3.3 pay

Beams

21 × 32 × 0.9mm

5.4 Support

Rose

6 × 40mm

10.8

General board

600mm × 600mm × 30mm

Stent

100~ 1000mm

2.8 pay

Beams

22 × 26 × 0.6mm

5.4 Support

Rose

6 × 32mm

10.8

Note: If special circumstances, can be customized according to customer demand. (This is not a precise numerical value calculation, the actual use may need to increase or decrease in individual parts).

Construction activity cross the floor to maintain that
→ To ensure that the construction of an elevated floor of the quality of construction not subject to cross the impact of our company to develop the following special safeguard rules, the Greek cooperation to comply with the common construction.
→ elevated position on the floor of the support (to whichever setting) does not allow any other construction obstructions placed.
→ has finished construction of the floor surface without the use of pre-delivery are not free to stampede, if construction of cross-borrowing needs of trampling on the floor, I have to be before the company agreed to be on-site management.
→ by the company after the management agreed to cross-borrow in the construction floor construction must comply with the maintenance of the following rules, if any of the provisions of construction, our company will be based on digital phase, a fine of 500 yuan each to show their punishment.

※ floor surface without the protection of the mosaic, are not allowed to use any construction work on the floor.
※ the surface of the floor should not be used for any heavy-duty scaffolding.
※ construction of the use of ladders, scaffolding at the bottom of the light must be tied with thick rubber.
※ Construction of the units is strictly prohibited the use of the surface of the floor in the paint, coatings, chemicals and materials.
※ Construction of the units is strictly prohibited to use a hammer or heavy objects hit the floor surface.
※ strictly prohibit the use of the surface of the floor tool and depicts a hard object.
※ If welding work must be on the floor plus a surface layer of protection, such as plywood, welding sparks come into contact with the floor is strictly prohibited.
※ strictly prohibit dumping below the surface of the floor.